May 2014 renovation begins….

Renovation began in the summer of 2014 at Cracroft ….. an outbuilding needed to be extended to provide the accommodation we had planned for Pibbles Nook….the site was excavated and cleared….foundations put in…..drains laid…..an outside wall had to be removed before the floor slab could be laid….bricks were then laid to create the new outside wall of the new  dining/sitting area….. part of the existing roof was retained and modified, and new attic trusses fixed over the extended part …..Velux roof lights were put into the newly created upstairs rooms and the roof felted and tiled….the work took  7 months to complete and we were water tight by Christmas 2014…..

 